AMiBA Engineering Telecon Minutes
13, Dec. 2001


Chair: K.Y. Lo
Participants: B. Martin, J. Payne, D. Emerson (USA), J. Peterson (South Pole)
M. Sinclair, M. Kesteven, W. Wilson (Sydney),
H. Wang, T.D. Chiueh, M.T. Chen, Y.J. Hwang, H.M. Jiang, W. Ho, P. Shaw (Taipei)

 

Action items

  1. Jeff/  Jeff will ask Rapadas to provide cost break down for Meridian lag correlator.
  2. Jeff/  Jeff & Rapadas will follow up to complete both lag correlator units and send to Warwick ASAP.
  3. Huei/  Huei will directly contact Joyce/TRW to get the module and technical details he need for InP HEMT design.
  4. Warwick/   Warwick will help to check the w-band LNA calibration data with Russell for Huei.
  5. Mike/   Mingtang Mike will figure out the size of enclosure he need to fit in the control hardware, and Mingtang will follow up to figure out power supply requirement and the specification of elecrical/electronical enclosure of whole prototype system.
  6. Mike/Bob/Philippe/   Mike&Philippe will specify the pedestal requirement for prototype mount, so that Bob could follow up to prepare the site accordingly.
  7. Bob/  Bob will follow up to get a firm quote from NRAO for OMT.

    Next meeting date/time: Thursday, 20, Dec. at 8:30AM Taipei time