AMiBA Engineering Telecon Minutes
22, Nov. 2001


Chair: K.Y. Lo
Participants: B. Martin, J. Peterson (USA)
M. Kesteven, W. Wilson (ATNF)
H. Wang, T.D. Chiueh, M.T. Chen, H.C. Lu, Y.J. Hwang, H.M. Jiang, W. Ho, P. Shaw (Taipei)

Action items

  1. Jeff/   Jeff will ship the lag correlator to Warwick on Monday, and send some connectors to Warwick ASAP.
  2. Jeff/Warwick   Jeff will discuss with Jeff Rapadas the cost of 351 correlators, he will have a detail discussion on this issue with Warwick offline as well.
  3. Leo/   Leo will generate block diagram and material list of LO/IF according the 13 arrays & conventional LO approach.
  4. Leo/   Leo will send the layout and specifications of the first stage IF amplifiers to Warwick today.
  5. Bob/Bob will follow up to work out the site acquisition agreement with MLO.
  6. Bob/   Bob will follow up to pin down the Hilo lab/office leasing agreement with CSO.
  7. Bob/ Bob will put together a draft agreement between RUCH/ASIAA for AMiBA, including budgets and mechanics by next week.



    Next meeting date/time: Thursday, 29, Nov. at 8:30AM Taipei time