AMiBA PROJECT WEEKLY MEETING MINUTES
Date:2 August 2001
Participants: B.Martin, H. Wang, J. Peterson, M. Sinclair, W. Wilson, H.C. Lu, W. Ho, C.S.Lien,
K. Lin, P. Shaw
Issues and Description
|
Action by
|
Output
|
MMIC |
|
H.Wang
M.Sinclair
H.Wang
M.Sinclair
|
Action item
Ongoing
Action item
|
Lag Correlator Hybrid |
|
W.Wilson
W.Wilson
K.Lin J.Peterson |
Action item
Action item Ongoing |
Receiver |
West asks Mal's help on checking whether we could remove the pin between coupler and transition.Mal will check the drawing and back to west by email. |
M.Sinclair |
Ongoing |
IF/LO |
|
Y.J.Hwang Y.J.Hwang
|
Ongoing Ongoing Ongoing
|
Platform/Mount/Dishes |
Bob is looking for a company to measure the accuracy of the prototype dish, and hopes to get those two small dishes from CMA in mid-August. |
B. Martin |
Ongoing |
Computer control ,software |
Homin is still waiting for the software board from Suzy Jackson; he also raised a purchase request for the up grade version of the LabView/Lab Window soft ware. Mal will follow up to check the status. |
M.Sinclair |
Action item |
Site Acquisition | ||
Bob will follow up and contact the Obv. People in Hilo | B. Martin | Ongoing |
Next Meeting |
7:30pm EDT,8:30am Taiwan, 10:30 Australia, 4:30pm Tucson/Thursday/August 9,2001 |