AMiBA PROJECT WEEKLY MEETING MINUTES

Date: 22 February 2001

Participants: K.Y. Lo, H. Wang, W. Warwick, M.Sinclair, M.T. Chen, H.C. Lu, Y. J. Hwang, R. Wei, W. Ho, Homing Jiang,

P. Shaw, Jean Cheng

Issues and Description

Action by

Output

MMIC

1.          Regarding the HPF purchasing issue, Leo has contacted the supplier, and is waiting for their quotation.

2.          As for purchasing the InP HEMT & HBT MMIC foundry run from TRW, Huei has sent a schedule plan to TRW, and Paul also sent information to TRW for NDA preparation. The purchasing process as Stracy Bui of TRW told Huei, we need to sign a NDA first; TRW will quote after, and then finally sign a contract. Bui said that the export license would be not sent to us until that contract signed.

3.          Regarding whether we could use those InP HEMT & HBT MMIC chips on the multipliers for prototype lag correlator and on the post amplifiers for prototype receiver, we should go ahead asking TRW. Warwick will draft out a letter, and forward it to Mal and Huei to read. Huei will also send a letter to TRW asking whether we could share the InP activities result with JPL to fabricate the LNA for AMiBA.    

4.          Good news from Todd, Huei says that JPL agrees to loan four LNA to us if those LNA are directly shipped to Hawaii site for prototype testing. According the test data provided by Todd, it seems better than the one purchased from NRAO. Huei will forward the test data to everyone to look, and collect more test data from Tadd.

5.         Fred says that doing all the testing and putting together things in Hawaii will help a lot, because we don't need ship back and forth between US and here, and that’s means we need to get a space to set up a lab in Hawaii. He asks Mingtang to list out what we need; how much space? What kind of instruments? And see what we can do.     

6.          Mingtang has talked to the designer of w-.band LNA while he visiting NRAO by last week, and the design engineer said to him that it is difficult to low down the noise temperature of that LNA further more. Science they only have two technicians in lab to make the w-band amplifiers, so they probably need one and half year to make 40 units of amplifiers. Fred says that the MIC amplifiers will be a back up to the MMIC amplifiers, since the MMIC amplifier will be $10k USD cheaper than NRAO amplifier per each.

7.          T.H. got some opinions back from Spacek on the measurement set up; Eugene & Mingtang have checked the power level of the analyzer last night. They will put an external attenuator during measurement and make calibration including the attenuator itself to low down the input power to the amplifier; they will re-measure that amplifier ASAP. Eugene says. 

8.          Eugene says that he is still waiting for more information of the mixer & HPF from Russian firm. Since Mal already agreed to use their design on the HPF for AMiBA, so Eugene will find a way to get the Russian firm’s quotation according to the drawing designed by Mal and his colleague.  

9.          As an alternative, Mal will modify the packaging design of the InP mixer module for the Sub-harmonic mixer application. Mal says that in the next week while Mingtang visit here, he will get some drawings together for that mixer, and see what they can do for prototype.  Eugene says that the module packaging for the prototype is ok, but for reducing the space of the whole module, it is better to put a LO input wave guide flange, and connect into the 3 dB coupler which is in the rectangular form. If we continue to use a connector for the LO input, then we will need a lot of transition. So he plans to run a 42 GHz LO in wave-guide, and this will save money and reduce space.   

10.       Eugene and Mingtang will visit Chungshang tomorrow afternoon to discuss the sub-harmonic mixer packaging as well as the w-band feed horn fabrication.

11.       Mingtang and Eugene will contact the Chungshang Institute to discuss the packaging issue for the Sub-harmonic mixer chips. And in the mean time, Mingtang will investigate the machining capability of the workshop in Chungshang. Since the OMT we are going to use, there is a lot of machining work on that, and Chungshang will be an alternative source for machining. 

12.       Huei says that there will be no wafer run for the 0.1um GaAs HEMT chips, and this will not effect the prototype fabrication. We will use the 0.15um GaAs HEMT chip, which designed, by Eugene, and Eugene will make a small tuning on that design in order to get some improvement. Huei says that they are going to make another design for the LO 42 GHz amplifier, probably put it in the 0.15um GaAs run by September.

H.C. Lu

 

 

 

 

 

W.Wilson

H. Wang

 

 

 

 

H. Wang

 

 

 

 

M.T. Chen

 

 

 

 

 

 

 

Y.J. Hwang

T.H. Chu

 

 

Y.J.Hwng

 

 

M.T.Chen

M. Sinclair

Y.J. Hwang

 

 

 

 

M.T. Chen

Y.J. Hwang

M.T. Chen

Y.J. Hwang

 

 

Y.J. Hwang

Ongoing

 

 

 

 

 

Action Item

 

 

 

 

Action item

 

 

 

Action item

 

 

 

 

 

 

Ongoing

 

 

 

Ongoing

 

 

Action item

 

 

 

 

 

Ongoing

 

 

Ongoing

 

 

Ongoing

Lag Correlator Hybrid

1.        A model of GaAs HBT from CIC /Taida has been sent to ATNF/Paul Robert.  

2.        Regarding the InP HBT multipliers, Warwick says a series of testing will be done in a couple of days. Huei asks Warwick to help to test the chip from a semi-conductor manufacturer by middle March, and Warwick agrees to check the lab program to see whether possible or not.  

3.        Warwick says that the final packaging for lag correlator is a very tricky issue, so all he can says is he is looking for an individual option at this moment. But there is not obvious path to go, and require a little bit of investigation to find out exactly what a way to go. 

4.        Regarding how to fit the prototype measurement with two correlators instead of four, Mike will bring this issue to the science meeting, Fred will follow up as well.

5.        Regarding the 16-element correlator basis on mixer using power divider circuit, Jeff says they are continuing to test the individual mixer using noise source. now they are going to measure the stability of the output, but they don’t have sensitive enough equipment to see the fluctuation of the output. So they will add the LNA to the output, and see if they can measure on that. In mean while, he is still waiting for out put of the producer for lag correlator, he will keep on pushing them. Jeff will be gone in the next two weeks to south pole, so he hopes something comes out when he backs.

P. Robert

W.Warwick

W.Warwick

 

W.Warwick

 

 

M.Kesteven

W.Warwick

J.Peterson

Ongoing

Ongoing

Ongoing

 

Ongoing

 

 

Ongoing

 

 

 

 

Receiver

1.        Mingtang is working on the material evaluation for receiver vacuum window, he has tested various dielectric material with the HP8510c vector network analyzer, which including ZOTEFOAM PPA-30 provided by Jeff, DYLITE provided by Mal, Mylar and Teflon. The a.m. test result has been sent to everyone to look

2.        Regarding the circular polarization issue, Mal will make a model according the information from Jeff.  

3.        Mingtang says that they almost finish the LO components layout arrangement, and now they are doing the thermos connection inside the dewar.

4.        Mingtang says that they only went over the testing for the OMT of Q-band in the last week, since the test instrument for W-band was broken down. He will keep on talking with NRAO people to settle down the corroboration proposal - designing and machining by NRAO, packaging and testing by us. 

 

M.T. Chen

 

 

 

M. Sinclair

M.T.Chen

 

M.T. Chen

 

Ongoing

 

 

 

Ongoing

Ongoing

 

Ongoing

 

IF/LO

1.        Regarding the over-order fiber laser system, Eugene will inform the maker that we would like to delete a unit from our order, and ATNF will take over that one and buy from them according the original price without extra charge. Eugene will ask the maker to send a quotation to Warwick as well. In the mean time, Paul will proceed the change order procedure with Taida accordingly.

2.        As to purchasing the optical fiber, Eugene will figure out the quantity we need. He will directly contact the Smithsonian people to see whether they could help us or not. Eugene received some cable information from Mal; Leo is working on that.

3.       As to the IF amplifier, Leo says that T.H. plans to use the chip form from HP, and he try to bind that chip by themselves. Warwick is concerning about the output power capability; he says that what we need for the LO amplifier is about ± 20dBM, and the HP one is only about 10dBM. Leo will discuss this issue with T.H. later.

4.        Regarding the design on Q- band sub- harmonic mixer, Eugene will make a back up plan for using the 0.15 um GaAs chip instead of the 0.1um GaAs chip. But for prototype, we will use the commercial module mixer integrated with the photonic mixer chips.

 

Y.J.Hwang.

P. Shaw

 

 

Y.J.Hwang

 

 

H.C. Lu

T.H. Chu

Ongoing

 

 

 

Ongoing

 

 

Action item

Platform/Mount/Dishes

 

 

1.        Bob has sent out a revised specification of mount & platform, a drawing of mount and some revised drawings of small dish to everyone to look. At pleasant, he is traveling to Germany to work with Vertex on the feasibility study about hexapod mount vs. conventional mount after that he will come and stay here from Feb. 26 to March 10.     

2.       Mingtang will bring the revised mount and platform specification as well as the mount drawing to the Chungshang Institute tomorrow afternoon. Paul will forward that revised information to Mike, and ask him to get a new offer from the Sidney Engineering Co. 

  

P. Raffin

B. Martin

B. Martin

 

M.T. Chen. P.Shaw

Ongoing

 

Ongoing

 

Action item

General issues

3.        Fred says that for every two week, now we have a coordination meeting with Bob, Warwick, Mike, Tzi-hong, Paul and he specifically to go over coordination issues. One issue was pointed out by Warwick is that the often time we make the decision and not announce properly or often we don't make Decision; the mount is an example, went from one 10 meters to three 2 meters, and now by 6 meter, we saw what happen, but we don't really know what exactly we are doing. Right now because of the cost reason mainly back to 6 meters. He finally got a report from Tzi-hong on behalf on the science team, from scientific examination of this issue, eventually conclusion is the 6 meters is ok. He will send that around for comment. As to the 6 meters mount, Bob of course will talk to Vertex, and we are going to send the revised specs to the Chungshang Institute, and see what they can do. We should try to get the company in Australia to take a look also.  

2.        Fred says that we are approaching the end of the first year and the beginning of the second year, he would like to take this opportunity to go over again at least the coordination level, some more detail on work packages, the project block into. Bob will be stay here about 10 days, Fred hope during that time, Bob will sit down and go over all the package in detail everybody here. We hope Bob could work out a work plan for mount and platform at that time as well. We really need to look at the cost what we have, he hopes Bob here in a week or so will start that process. Regarding the time schedule for prototype, it seems is not clear what exactly in our mind. So after this phone call, Fred will draft something and send it out around to make it clear.  

  

 

 

Traveling

Mingtang visiting ATNF by Feb.27 ~ March 4

Next Meeting

7:30pm EDT, 8:30am Taiwan, 10:30 Australia, 4:30pm Tucson/Thursday/March 01, 2001