AMiBA PROJECT WEEKLY MEETING
MINUTES
Date: 15 February 2001
Participants: B.
Martin, H. Wang, W. Warwick, M.Sinclair, H.C. Lu, Y. J. Hwang, W. Ho, Homing
Jiang, P. Shaw, Jackie Wang, Jean Cheng
Issues and Description |
Action by |
Output
|
MMIC |
||
1.
Regarding the HPF purchasing issue, Leo will contact the supplier and
tell them we would like to purchase the first 5 units for prototype, and we
will purchase 35 units more once the first 5 units is accepted by testing,
and ask the supplier to give their best offer to us. 2.
As for inquiring TRW for the price of InP HEMT & HBT MMIC foundry
run, Huei will send a schedule plan to TRW. Huei thinks the InP foundry run
schedule should be based on the existing design of JPL, and we should loan
some modules from JPL to verify whether they are good for our prototype or
not, and if JPL agree to loan some module to us. Another back up action is to
put our design on ATNF¡¦s HBT chips, since a wafer run t will be carried on in
June this year for their own purpose, Mal says. Mal agree to talk about that
idea with the people in charge in ATNF, and then contact TRW through the
existing contract channel to see whether TRW accept the a.m. collaboration on
the InP HBT wafer run for AMiBA. And we should point out to TRW that the InP
chips will be directly shipped to Hawaii or via ATNF to Hawaii. l
Schedule plan for InP HEMT MMIC: 1st run - end of 2001, 2nd run - 3rd
quarter of 2002; l
InP HBT MMIC: 1st run ¡V 2nd quarter of
2002. 3.
Since we got approval for the InP export license, so Todd thinks they
probably could ship the units through TRW on the export license. Huei will
talk with TRW people to see whether they could do this service on us. 4.
Jean already sent a copy of the InP LNA measurement result from NRAO
to everyone to look, and in the mean time Mingtang inputs two plots of the
Trx VS Frequency for the NRAO LNA on web site as well. He will talk with the
designer when he visit NRAO by next week, and see if they could make the rest
of 2 units better. 5.
No response from Spacek about mixer and amplifier, and T.H. will keep
in touch with Spacek, Eugene says.
Eugene got a quotation for mixer and HPF from Russian firm, it is
$3,000 USD each mixer and $1,200 USD each HPF, deliverable in 8 weeks, and
the conversion loss is only 6~8 dBA for the mixer. This will be an option for
the post amplifier. 6.
As an alternative for the past amplifier, Mal will take a look at the
InP mixer chips which they have designed for their own, to see if they can
modify the package design to suit our needs. Mal will follow up to collect
all drawings for machining and packaging, and send them to Mingtang and Bob.
In the mean time, Mingtang and Eugene will contact Chungshang Institute to
see if they can do the machining & packaging for that mixer chips. 7.
Mingtang and Eugene will contact the
Chungshang Institute to discuss the packaging issue for the Sub-harmonic
mixer chips 8.
Regarding the wafer run for the 0.1um GaAs HEMT chips, Huei says due
to TRW raise their price from $120k USD to $185K USD, and is difficult to get
money from NSA /CIC to make the wafer run in this year. However this change
will not affect the prototype fabrication. 9.
Due to the problem of
the Specek amplifier, we need to find an optional post amplifier for
receiverMal says they don¡¦t have the suitable GaAs
MMIC chips for our post amplifiers needs. however Mal will keep on looking
for the opportunity to use the ATNF InP HBT chip for the post amplifier. |
H.C. Lu
H. Wang M. Sinclair H. Wang M.T. Chen T.H. Chu M. Sinclair M.T. chen Y.J. Hwang M.T.Chen Y.J.Hwng M.T.Chen H.C. Lu M. Sinclair |
Action item
Action item Ongoing
Ongoing Action item Ongoing Ongoing |
Lag Correlator Hybrid |
||
1.
Huei says a model of GaAs HBT from CIC /Taida shall be provided to
ATNF/Paul Robert in this March..
2.
Regarding the InP HBT multipliers, Warwick says the packaging test is
under way. 3.
Eugene contacted the ACX in Taiwan; he got an offer back from ACX,
and forwarded it to Warwick as well. According their offer, Warwick thinks
the biggest problem is they don¡¦t have experience in doing the print
resistor, and we have to use this resistor in the lag correlator. So he
thinks we need to look for some other manufacturers. Warwick will do it in a
couple of weeks. Ray says the IC chips will be back from CIC in March, and
before that he is working on another chip design of voltage converter, it
will be completed in March also. Regarding the LNA, it is difficult to find
that chip in die form; Ray will keep on looking for that. 4.
Warwick asks Bob does he hear any comment back from the science team
about how to fit the prototype measurement with two correlators instead of
two. Since Bob didn¡¦t attend that telecon, so Warwick will follow up with
Michael. 5.
Regarding the 16-element correlator basis on mixer using power
divider circuit, Jeff says they are continuing to test the individual mixer
using noise source. now they are going to measure the stability of the
output, but they don¡¦t have sensitive enough equipment to see the fluctuation
of the output. So they will add the LNA to the output, and see if they can
measure on that. In mean while, he is still waiting for out put of the
producer for lag correlator, he will keep on pushing them. Jeff will be gone in
the next two weeks to south pole, so he hopes something comes out when he backs.
|
H.Wang W.Warwick W.Warwick W.Warwick R. Wei W. Warwick Peterson |
Ongoing Ongoing ongoing Ongoing Ongoing Ongoing |
Receiver |
||
1.
Mingtang tested the window material, which supplied by Jeff in the
last week; he found that material is very good. Besides its cost is much
cheaper than the commercial one. He will finish the test on that material and
send the results to everyone to look. Mal also will send a sample to Mingtang
as well. 2.
Warwick says he received the resent work plan of Mingtang by email
from Jean, and it is readable. So Jean will follow up to resent all work
plans to everyone as she did before. As to the project schedule, Jean will
resent the schedule in the Microsoft Project 98 version as well. 3.
Regarding the circular polarization issue, Mal has read the
information from Jeff. and he will be modeling on that. He will let
us know what is going on afterward. 4.
Mingtang will visit ATNF from Feb. 27 to March 4, he will discuss
with Mal about the receiver design in details, including feed horn. 5.
Eugene says that our mechanical engineer West Ho and himself almost
finish RX components layout in the cryostat, the only problem is we need a
little bit higher space inside the chamber to put the stainless wafer guide
flange for the temperature difference. They also generate some special wave-guide
section drawing, and will send them to the firm in USA for quotation. |
M.T. Chen J. Cheng M. Sinclair M. Sinclair M.T. Chen M.T. Chen Y.J. Hwang W. Ho |
Ongoing Action item Ongoing Ongoing |
IF/LO |
||
1.
Warwick has received the technical data of fiber laser system from
Eugene, and he agrees to buy one from IAA. Eugene will talk with Warwick
about the purchasing procedure in detail afterward. 2.
As to the optical fiber, Bob suggests Eugene should look for other
alternative in the market, and discuss with John about alternative as well.
In the mean time, Bob will try to get the quotation from Sumitomo through the
Smithsonian people. Mal will send some cable information to Eugene to look. 3.
Regarding the Q band sub harmonic mixer design, Eugene will make a
back up plan for using the 0.5 um GaAs chip instead of the 0.1um GaAs chip.
He will continue looking for a commercial available MMIC chips on that mixer. |
Y.J.Hwang. W. Wilson Y.J. Hwang B. Martin M. Sinclair Y.J.Hwang |
Ongoing Action item |
Platform/Mount/Dishes |
|
|
1.
Philippe received some drawings of the small dishes from Bob; he will
start working on those drawings by today. Bob will work out a summary of the
optics in the coming day. 2.
As to the mount, Bob will work out some drawings and send them over
to Vertex and Chungshang Institute before he visit vertex by next Thursday
& Friday, after that he will come to Taipei. The general overview on the
prototype system including time schedule in a regular basis is necessary: Paul will place
the work plan of each sub-system in prototype as well as the time schedule on
the web site, so everyone could take a look. We will talk on those work plans
in detail by next week. |
P. Raffin B. Martin B. Martin |
Ongoing Ongoing |
Next Meeting |
||
7:30pm EDT,
8:30am Taiwan, 10:30 Australia, 4:30pm Tucson/Thursday/Feb. 22, 2001 |