AMiBA PROJECT WEEKLY MEETING MINUTES
Date: 21 December 2000
Participants: H.
Wang, W. Warwick, M. Sinclair, M.Kesteven, M.T. Chen, H.C. Lu, Y. J. Hwang, P.
Shaw, J. Wang, Jean Cheng
Issues and Description |
Action by |
Output
|
||
MMIC- W- Band InP HEMT LNA |
||||
1.
Leo presents a simulation result on HPF, comparing the ¡§image
rejection ratio in dB¡¨ among the specs of original, ATNF and proposed one.
Due to the increase value of image rejection ratio compared with the original
specs is only 1.7dB, Huei suggests Leo to make a spread sheet further on that
simulation in order to verify whether it is worth to revise the original
specs or not. Warwick says that if we increase the low frequency of the IF up
to one GHz that will improve greatly, and he thinks that¡¦s going to happen.
Any correlator we use is unlikely to go much below 1.5 GHz. So we should use an
IF of 1~20GHz frequency range, and we will no go better than that. Leo will
talk to T.H. about this issue. In the mean time, Mal is working on the filter
fabrication and testing. 2.
Huei have sent the initial layouts of the InP HEMT chip to JPL; he
has discussed the noise model with Todd, and is doing the final trading on
design. As to loan some modules from JPL, Todd has promised to write a task
description report to NASA for approval. 3.
Regarding the Specek's amplifiers,
Leo say that T.H. told him the Specek¡¦s agent in the States has received
the amplifiers, and he thinks the delivery date may be after new year. |
H.C. Lu H. Wang T.H. Chu |
ongoing ongoing |
||
Lag Correlator Hybrid |
||||
1.
Huei received a revised specs for the Gilbert Cell Multiplier from Warwick,
and the noise performance for the ATNF InP HBT multiplier may not be
good enough for AmiBa According the calculation result, the multiplier
adds about 10% to the output fluctuations therefore decreasing the sensitivity
by 10%, and it is equivalent to a 10% increase in Tsys. Warwick will
discuss this result further with Michael to see how to solve the problem.
Warwick will provide the technical data of InP HBT chips to Huei. Huei
will ask students doing a noise analysis on the circuit of GaAs HBT
process. 2.
Regarding the InP HBT multipliers, Warwick says that wafers have not
gotten back from TRW yet, and in the mean time Paul has been getting the
packaging and test fixture ready. He is also continuing to talk to the ACX in
Taiwan about the LTC module for lag correlator using HBT multipliers. 3.
Ray has sent Warwick
a lot of information about the possible DC amplifier to follow the multiplier.
Warwick says that in line with the latest information we have on noise,
we need to reconsider there exactly what noise performance we need.
Ray and Warwick will keep on looking for the available commercial chips.
|
W. Wilson H.Wang W. Warwick |
ongoing ongoing |
||
Receiver |
||||
1.
As per request, Mal will provide a temperature sensor board to Mingtang. 2.
Regarding the collaboration proposal
on the development of NRAO OMT, John is working on pricing and time
schedule in details. Bob will follow up this issue with John. 3.
Regarding the vacuum window material,
Mal will send a sample to Mingtang, and then Mingtang will do the transmission
measurement on it. 4.
As to the multi hole coupler, Mal
says that a real one will be worked out in a couple of months. 5.
Yugene will provide Mal the technical data, price and company information
of the noise source, which made in Russia. 6.
Mal will look at the summary on
receiver design, which prepared by Mingtang; he will get back to Mingtang
if any thing is needed to clarify. |
H.C. Lu B. Martin Y.J.Hwang M. Sinclair |
ASAP ongoing ASAP ASAP |
||
IF/LO |
||||
Yugene will send the technical data of
fiber laser system to Warwick; Warwick will take a look to see if it is
suitable for his need. |
T.H. Chu |
ASAP |
||
Platform/Mount/Dishes |
|
|
||
1.
We are waiting for the final quotation for the prototype dishes from
the firm ¡§Composite Mirror Application, Inc.¡¨ Bob and Kingsley will generate
some preliminary drawings to show the interface between dish, receiver and
mount, and send them over to Mingtang and Philippe to look at. 2.
Bob is working on a quotation from Vertex for the feasibility study
and pricing according the different specification of mount and platform. We
hope to get it done in the beginning of Jan. |
B. Martin B. Martin |
ongoing ongoing |
||
Next Meeting |
||||
7:30pm EDT,
8:30am Taiwan, 10:30 Australia, 4:30pm Tucson/Thursday/Jan. 4, 2001 |
||||