AMiBA PROJECT WEEKLY MEETING MINUTES
Date:14 December 2000
Participants: B.
Martin, H. Wang, T.H. Chu, W. Warwick, M. Sinclair, B. Sault, M.T. Cheng, Y. J.
Hwang, P. Shaw, Jean Cheng
Issues and Description |
Action by |
Output
|
||
MMIC- W- Band InP HEMT LNA |
||||
1.
Huei, T.H. and Leo met Mal, Russell, Paul and George last week in Sydney.
Huei discussed about the update HEMT test result with Paul, and also passed
the Sub Harmonic Mixer chips to Russell to test. In the meeting, they also
discussed about the wave guide drawing, and go over the Taida Gib Cell HBT
multiplier with Paul. Huei asked Paul help us to finalize the multiplier
specs according the new design of InP multiplier. Paul is working on that, he
will finish it and send it over to Huei today or tomorrow. 2.
Leo got the HPF specs from Mal last week in Sydney, he will do some
simulation in the lab to verify the difference of specs between Mal and Leo.
He will present the simulation result to everyone in next week. 3.
Huei have sent two designs for the InP HEMT chip to JPL, and
currently one of his students is working on the third design. He will finish
it and send it to JPL as well. As to loan some modules from JPL, Todd will
write a task description report to NASA for approval today.
4 As for
the 0.1um GaAs HEMT, Huei says that they are still working on the error checking,
he will check the progress with CIC early next week. .. 5. Regarding the Wave-guide filter, Huei passed a copy of
the drawing form AT to Prof. Wu. Wu’s student is doing the simulation
in parallel. 6.
Regarding the InP MMIC, Mal says that 3 w-band amplifiers has been
tested, and the result is quite encourage, but a little bit disappointment
about the noise band width. 7.
Regarding the Specek's amplifiers, T.H. says that he hopes to receive
the stuff in a couple of days. He will test them once received. |
H. Wang H.C. Lu H.Wang H.Wang M. Sinclair T.H.Chu |
Dec. 14 ongoing ongoing |
||
Lag Correlator Hybrid |
||||
1.
Regarding the InP HBT multipliers, Warwick says that wafers have not
gotten back from TRW yet, and in the mean time Paul has been getting the
packaging and test fixture ready. He is also continuing to talk to the ACX in
Taiwan about the LTC module for lag correlator using HBT multipliers. 2.
Ray asks if he need to design a new LNA/LPF chip? Warwick has
discussed this issue with Tzi-Dar, both agree to look at the market if they
can find the suitable commercial chips. Currently Ray is looking at it
further. 3.
Paul talked to CIC person in charge Mr. Wang about the
large fabrication of 0.35 micron CMOS for us, his response is quite
promising. He think it should be OK to cover our requirement in the
fabrication program of 2001, and the price for 15oo ICs is about 2M NTD. |
W. Wilson Ray Wei P.Shaw |
ongoing Ongoing |
||
Receiver |
||||
1.
Last week, in Sydney, Leo discussed the layout with Mal, Mal gave him
a lot of advises. He will discuss the details with Mingtang after meeting. 2.
Regarding the collaboration proposal on the development of NRAO OMT,
John is working on pricing and time schedule in details. Bob will follow up
this issue with John. 3.
Regarding the vacuum window material,
Mal provides Mingtang a copy of NRAO Memo of “Quasi-optical vacuum widow/A
study on material for a broadband millimeter wave”. |
H.C. Lu B. Martin |
ASAP ongoing |
||
IF |
||||
Last week, in Sydney, T.H. talked with George
about the IF equalizer, George gave some advise on the implementation to
improve the frequency response of equalizer. So he will modify the circuit
layout design accordingly. |
T.H. Chu |
|
||
Platform/Mount/Dishes |
|
|
||
1.
Bob received a quote for dishes from Composite Mirror Application,
Inc., the price is quite attractive. He will meet with Kingsley and iterate
the dish design. And then they will meet CMA on Saturday about pricing and
how to proceed with getting a contract in place. He and Kinsley will work out
preliminary drawings to show the interface between dish and receiver, and
send them over to Mingtang and Philippe end this week. 2.
Bob asks Michael to take look on the approach to the whole system in terms
of number of elements, and the certain way of approach or concept what we are
going to do, there is the modularity issue of the correlator and how we are
doing the platform and dish, to figure our the optimal number for all of key
elements. He also would like ask Warwick to take a look at how strong is the
couple, if we cut the cost in the project, and how strong they got the of
correlator cost projection going with the end square, and how much is the
consequence, how many % in size. Bob really like to draw out some conclusion
about where we should go with how many elements, and how we should approach
this in budgetary term. In the mean time, Paul will update the cost
projection on what we have, and send it over to Warwick and Michael to look
at. 3.
Regarding the outstanding configuration issue, Bob and Fred will
discuss it with the science team today. He will also talk to vertex about the
design iteration today as well. Our aim to find out the priority of the
science goal, and develop an optimal engineering solution. |
B. Martin B. Martin M. Kesteven W. Warwick B. Martin |
ongoing Ongoing ongoing |
||
Traveling |
||||
Bob/ Dec 22~Dec 28 |
||||
Next Meeting |
||||
7:30pm EDT, 8:30am
Taiwan, 10:30 Australia, 4:30pm Tucson/Thursday/Dec.21, 2000 |
||||
Please note
:the meeting on Dec.28 will be cancelled. |
||||