AMiBA PROJECT WEEKLY MEETING
MINUTES
Date: 2 November 2000
Participants: W.
Wilson, M. Sinclair, M. Kesteven, B. Sault, M.T. Chen, C.H. Lu, Y.J. Hwang, P.
Shaw
Issues and Description |
Action by |
Output
|
||
MMIC- W- Band InP HEMT LNA |
||||
1.
Regarding the Sub Hamonic Mixer¡¦s chip test at ATNF, Huei asked Mal
last week whether AT can make three more mixer isolation measurements. Mal
says that they are planning to do at least two of those in late Dec. once
they finish the installation of receiver. But on measurement has a lot of
difficulties been doing, because of it requires a certain device, which we don¡¦t have. 2.Huei says that the first
design for the InP HEMT MMIC is ready, and now is waiting for the wafer test data from JPL. Todd told him that he needs two weeks more
to work out that test data. Fred says he will visit Pasadena in a week time. So Huei will inform Todd
about Fred visit and ask him to arrange an appointment with the person in NASA who is responsible for
the export license approval.
3.As for the 0.1um GaAs
HEMT, Huei says the chip is ready shipped to TRW. There are some arguments on
contract terms, and need to solve with TRW . 4.As to the export license
application for the InP HEMT of TRW, Huei says Joyce told him that the review process is still ongoing at the State Department He is
expecting to get a final decision on that issue by early November. 5.Wave-guide filter ¡V Huei received some experiment data
from Mal by fax, Mal will provide some drawings to Huei as well, and Huei will forward those data
and drawings to Prof. Wu. This would be a good reference to Prof. Wu to develop his design in
parallel. (Mal is modifying the existing design of 80 GHz to 85 GHz as we need.) As for the prototype receivers,
Mal suggests Mingtang to investigate if he can find the required filters in the market. 6.Leo got a HPF quotation
from Quinstar; the price is $1,000USD for each, but it would be $250USD each
if we once order 40 units; specs are 80.5~105GHz, 84GHz at 3dB cut off,
insertion loss 27db at 82 GHz. They need 60 days to deliver the first 4
units, and another 30days to deliver the remaining 36 filters. Mal says that
it sounds a pretty good job on that design, and price also looks good. Leo will
contact the supplier to confirm their specs could meet our requirement.
George Grace provides some information of wave- guide filter to Leo. How to
handle the thermal and expansion problems of wave-guide, Mal suggests that he
would look carefully at any shaping the wave-guide in couple, and using the
thermal stainless steel guide in straight section with thermal isolation
only, and keep them straight. 7.Regarding the InP MMIC,
Mal says that there are two things happening here now; they are currently testing
some K-band amplifier added wafer run with the 3mm MMICs around, doing the
cold measurement on amplifier to see the material behavior under cryogenics
condition, and the noise temperature in cooler. He found some problems with
the isolation of amplifier, a lot of gains on small chips. Several fixes they
are trying at this moment, and basically he believes it is the coupling
problem. He suspects we may have the same problem for W-band chips. 8.As far as the W-band
chips concern, Mal says that the chips have been tested at room temperature,
and currently there
are 6 chips have been mounting on the amplifier body, they are constructed by
this moment. And he hopes they would have several amplifiers tested by next
week at room temperature. There is also the 3 mm amplifier design on move. 9.According to the
contract terms, Specek should pay the delay penalty to Taida. Because of the
deviation on the conversion loss with the specs is not much, and it
can be compensated by other IF components. So Prof. will inform the above decision to Specek. 10.Regarding the NRAO
W-band amplifiers, Mintang asked for some mechanical drawing, bias drawings
and circuit drawing from NRAO, but without response. He will resend a request
to NRAO today. |
H. Wang M. Sinclair H.Wang H.Wang H. Wang H.C. Lu H.C. LU M. Sinclair M. Sinclair T.H. Chu M.T. Chen |
Late Dec. ongoing ongoing ongoing Done ongoing ASAP ongoing ASAP ongoing |
||
Lag Correlator Hybrid |
||||
1. Jeff says if we
could use the alumina for the transmission line in the correlator, the area
required for the whole correlator would be 5 times smaller. Currently some of
his students are working on this study and doing some calculation. And it needs
a couple of weeks more to know the answer. 2. Regarding the
prototype mixer based lag correlator, Jeff will inform the update status by
next week 3. Warwick says
that they almost complete measurement on the HBT Gilbert Cell multiplier
wafer, and the result looks like promising to use that multiplier up to 20GHz
bandwidth. Warwick will put together all information and send over to
everyone in the next few days. 4.The ACX Company has
answered Warwick¡¦s enquiry about the correlator element fabrication by email, they also
raised some questions to us. Warwick has answered ACX¡¦s questions, and Paul
forwarded Warwick¡¦s response to ACX as well. 5. Warwick says he did few
measurements on the narrow band prototype correlator and it seems going very
well and it is working quite nicely at the 3 GHz bandwidth. And the next
thing is to do the noise measurement. 6.Huei says that they
finished the design work on the Gilbert Cells Multiplier, but there are some Problems unsolved. So he
will talk to Paul Robert to find out solution. |
J. Peterson J.Peterson W. Wilson P. Shaw W. Wilson H. Wang |
ongoing next week soon done ongoing ASAP |
||
Receiver |
||||
1.
Mingtang is working on the Dewar layout; he is waiting for the mount
layout, wish to know the supporting interface between receiver and mount. He
is still working on the components in the deward. (Paul
got one layout from J. Kingsley this morning. Kingsley says that he will send
over the rest of file to Paul once he backs from Sweden in next week.) 2.
Regarding the collaboration proposal on the development of NRAO OMT,
Mingtang thinks that is a good idea, but still needs Fred¡¦s approval. Paul
asks John to provide cost breakdown and detail time schedule to us
accordingly. John agrees to do so; he will work out this information together
with J. Kingsley. 3.
Mingtang is working on
the feed horn detail design; he has worked out some calculation and
circulated it to everyone last week. Mintang sets up a priority for horn
design ¡V 1.to fix the feed horn design first; 2.to decide whether we will use
the multiple hole coupler or not; 3. to look at the OMT parts to see what
kind of things would be putted in and then consider the physical design of
phase shifter. Mingtang says that according the prototype dish specification
- the F ratio is 4; it would be very difficult for us to design a 14 degree
angle feed horn. And this problem should be clarified further with Bob. Mal
says that according the production schedule, they should complete their own
prototype feed horn by Feb. or March next year. Mingtang thinks it would be
good for us if we could use the AT feed horn design on AMiBA. 4.
Jeff says that he has made a design for feed horn year ago, and it is
very easy to machine. He will send that design data to Mingtang to look at. 5.
Regarding the ¡§circular & linear systems¡¨ issue, Mal, Michael and
Jeff have been working on it. But for the prototype, we will use the linear
one. 6.
Jeff will send the window foam material information to Mingtang once
he got it. Mal will send some window foam information
to Mingtang as well. |
M.T.Chen H.C. Lu J. Payne C.T. Mingtang J.Peterson J. Peterson M. Sinclair |
ongoing ASAP ongoing Ongoing DONE ongoing |
||
LO/IF |
||||
1.Eugene just
generates a NRAO visit report today; he will circulate it to everyone to look
at. We will put it on the ASIAA web site, and welcome
everyone to take a look and to comment. 2.Eugene is
working on ¡§the wideband LO noise effect calculation¡¨; he will send over to
everyone to look at once finished. 3.Eugene says
that the fabrication run in TRW for the 0.15£gm GaAs PHEMT
process has been delivered to Taipei. This is his first iteration design on
the Subharmonic Mixer. Eugene ask Mal whether AT is able to test that chip
for us by Mid. Nov. Mal says that their lab is very busy now, and he thinks
it would be not possible to do it for us until early next year. So Eugene
will start to make simulation on chip and to finish the package design. |
Y.J. Hwang Y.J. Hwang Y.J.Hwang |
DONE DONE ongoing |
||
Platform/Mount/Dishes |
|
|
||
1.Jeff doesn¡¦t think the caesarian
could work with the 30cm antenna due to its high ground pick up. He will do some quantitative analysis to demonstrate this
case. 2.Regarding the height of
ground shield for our antenna, Bob requests Michael to ask their expert to
verify what size is good for us? 3.Mingtang says our new
engineer assistant C.W.Lu fould a local expert in the field of Hexapod. The expert, Prof. Perng, leading a lab in the Department of
Power mechanical Engineering of The Tsing-Hua University. Prof. Peng has more
than 10 years research experience on Hexapod, and he is very interest in the
AMiBA work. So Mingtang will invite him over to ASIAA to give a talk on what
he knows and what he think about our mount. Mingtang will organize lunch talk
for Prof. Peng on Nov.9. |
J. Peterson M.Kesteven M.T. Chen |
ASAP ongoing ongoing |
||
Site acquisition |
||||
Bob says that he plans to
visit Mauna Lao Observatory by the second week of November, to take a look on
site and see what the possibility is and how we proceed. |
B. Martine |
Ongoing |
||
Prototype
Specification and Project Book |
||||
1. Ravi inputs a report on
the topic of ¡§Confusion & AMiBA SZE Survey¡¨; you can also read it on the
AMiBA web page. 2. As to the secondary
mirror supporting structure, Jeff will collect some material information and
send it over to everyone to look at. |
J. Peterson |
ASAP |
||
Visitor |
||||
Darrel Emerson Nov. 9~13 / J. Payne Nov. 9~16/ B. Martin Nov. 2~13 |
||||
Traveling |
||||
|
|
|
||
Next Meeting |
||||
8:30pm EDT,
8:30am Taiwan, 10:30 Australia, 5:30pm Tucson/Thursday/Nov. 9. 2000 |
||||