AMiBA PROJECT WEEKLY MEETING
MINUTES
Date: 26,October 2000
Attendants: J.
Peterson, H. Wang , T.H. Chu, M.T. Chen, C.H. Lu, Y.J. Hwang, C.W. Lu, P. Shaw,
J. Wang
Issues and Description |
Action by |
Output
|
|
MMIC- W- Band InP HEMT LNA |
|||
1. Regarding the
Sub Hamonic Mixer¡¦s chip test at ATNF, Mal says the target date to do that
test should be in the end of this month. Huei received an insulation
measurement result for the SHP mixer chip from Mal. 2. Huei says that
the first design for the InP HEMT MMIC is ready, and now is waiting for the
wafer test data from JPL. Todd told him that he needs two weeks more
to work out that test data. Fred says he will visit Pasadena in a week time. So Huei will inform Todd
about Fred visit and ask him to arrange an appointment with the person in NASA who is responsible for
the export license approval.
3. As for the
0.1um GaAs HEMT, Huei says the chip is ready shipped to TRW. There are some
arguments on contract terms, and need to solve with TRW . 4. As to the
export license application for the InP HEMT of TRW, Huei says Joyce told him
that the review process is still ongoing at the State Department He is
expecting to get a final decision on that issue by early November. 5. Wave-guide
filter ¡V Huei received some
experiment data from Mal by fax, Mal will provide some drawings to Huei as well, and Huei will forward those data
and drawings to Prof. Wu. This would be a good reference to Prof. Wu to develop his design in
parallel. (Mal is modifying the existing design of 80 GHz to 85 GHz as we need.) As for the prototype receivers,
Mal suggests Mingtang to investigate if he can find the required filters in the market. 6. As per NRAO¡¦s
request, we released a formal purchase order to NRAO for purchasing the 4
units of 82~106 GHz amplifiers. Mingtang will directly contact NRAO¡¦s
engineer in order to get some technical data, including the layouts of
amplifier. 7.Mal
says that he received a reminder the wafer is back this week, the plan is to
test more chips in the
next couple of weeks. All the hardware of the amplifiers blocks in
completed, so he expects to start to test that w-band InP LNA chips sometime
by end next week. So he hopes to work out some test results in three weeks. 8.According to the
contract terms, Specek should pay the delay penalty to Taida. Because of the
deviation on the conversion loss with the specs is not much, and it
can be compensated by other IF components. So Prof. will inform the above decision to Specek. |
H. Wang M. Sinclair K.Y. Lo H.Wang H.Wang M.Sinclair H. Wang M.T. Chen H.C. Lu MT. Chen H. Wang T.H. Chu |
DONE ongoing ongoing ongoing ongoing ASAP ASAP ASAP ASAP |
|
Lag Correlator Hybrid |
|||
1. Jeff says if we
could use the alumina for the transmission line in the correlator, the area
required for the whole correlator would be 5 times smaller. Currently some of
his students are working on this study and doing some calculation. And it needs
a couple of weeks more to know the answer. 2. Regarding the
prototype mixer based lag correlator, Jeff will inform the update status by
next week 3. Warwick says
that they have made some measurement on the HBT Gilbert Cell multiplier
wafer, the result is quite similar with the simulation, and he think there is
a possibility to use that multiplier up to 16 to 20GHz bandwidth. Warwick
will collect more measurement data, generate a report, and send over to Huei
and Jeff to take a look. 4.The ACX Company has
answered Warwick¡¦s enquiry about the correlator element fabrication by email, they also raised some
questions to us. Warwick right now is working on those questions. 5. Warwick says he got the
low bandwidth prototype working now, got the first spectrum the other day,
and it is working quite nicely at the 3 GHz bandwidth, simulate the result of
Andy Harris shown. He is doing a test on it at this moment, trying to figure
out what the frequency response has on the performance. And he thinks it
looks quite promising to work with the 3 GHz bandwidth correlator. 6.Huei says that they
finished the design work on the Gilbert Cells Multiplier, but there are some Problems unsolved. So he
will talk to Paul Robert to find out solution. |
J. Peterson J.Peterson W. Wilson H. Wang |
ongoing next week ongoing ASAP |
|
Receiver |
|||
1.
Mingtang is working on the dewar layout; he is waiting for the mount
layout. He has not decided yet the overall size, because he is still waiting
for the data of some components in dewar, e.g. wave-guide. J.
Kingsley is working on the mount layout; Paul will contact Jeff to know the
status. Leo will speed up the components sourcing progress to collect
sufficient data in order to finalize the layout design ASAP. (Paul got one
layout from J. Kingsley this morning. Kingsley says that he we will send over
the rest of file to Paul once he backs from Sweden (next week). 2.
Regarding the collaboration proposal on the development of NRAO OMT,
Mingtang thinks that is a good idea, but still needs Fred¡¦s approval. Paul asks
John to provide cost breakdown and detail time schedule to us accordingly.
John agrees to do so, he will work out this information together with J.
Kingsley. 3.
Mingtang is working on
the feed horn detail design; he has worked out some calculation and circulated
it to everyone last week. AT has a prototype compact corrugated feed horn; he
is discussing it with Mal. 4.
Jeff says he made a design for feed horn year ago, and it is very
easy to machine. He will send that design data to Mingtang to look at. 5.
Regarding the ¡§circular & linear fits in the system¡¨ issue, Jeff
has been discussing with Michael and Bob Sault about by email back and forth,
and they think a phase shifter can be used. Mingtang says he will use the
simple one ¡V the linear system for prototype, and he will leave some space in
deward for phase shifter if we decide to use the circular system after. Jeff,
Mingtang, Michael and Bob will keep on discussing on this issue. 6. Jeff will send the window foam
material information to Mingtang once he got it. |
M.T.Chen H.C. Lu J. Kingsley J. Payne C.T. Mingtang M.T. Chen J.Peterson |
ongoing next week ASAP ongoing ASAP ASAP |
|
LO/IF |
|||
1.Eugene just
generates a NRAO visit report today; he will circulate it to everyone to look
at. We will put it on the ASIAA web site, and welcome
everyone to take a look and to comment. 2.Eugene is
working on ¡§the wideband LO noise effect calculation¡¨, he will send over to
everyone to look at once finished. 3.Eugene will
visit Japan to participate the ALMA Photonic Meeting by Nov. 7&8. |
Y.J. Hwang Y.J. Hwang |
DONE ASAP |
|
Platform/Mount/Dishes |
|
|
|
1.Jeff doesn¡¦t think the caesarian
could work with the 30cm antenna due to its high ground pick up. He will do some quantitative analysis to demonstrate this
case. 2.Regarding the height of
ground shield for our antenna, Bob requests Michael to ask their expert to
verify what size is good for us? 3.Mingtang says our new
engineer assistant C.W.Lu fould a local expert in the field of Hexapod. The expert, Prof. Perng, leading a lab in the Department of
Power mechanical Engineering of The Tsing-Hua University. Prof. Peng has more
than 10 years research experience on Hexapod, and he is very interest in the
AMiBA work. So Mingtang will invite him over to ASIAA to give a talk on what
he knows and what he think about our mount. Mingtang will organize a meeting
sometime during the second week of Nov. |
J. Peterson M.Kesteven M.T. Chen |
ASAP ongoing ongoing |
|
Site acquisition |
|||
Bob says that he plans to
visit Mauna Lao Observatory by the second week of November, to take a look on
site and see what the possibility is and how we proceed. |
B. Martine |
Ongoing |
|
Prototype
Specification and Project Book |
|||
1. Bob and Fred asks Michael,
Ravi and Bob to take a close look at some technical related science issues, e.g. UV coverage with current design on platform and drift
scanning techniques, observation strategy and photonic delay line. 2. As to the secondary
mirror supporting structure, Jeff will collect some material information and
send it over to everyone to look at. |
M.Kesteven J. Peterson |
Ongoing ASAP |
|
Visitor |
|||
Darrel Emerson Nov. 9~11 / J. Payne Nov. 9~16/ B. Martin Nov. 2~13 |
|||
Traveling |
|||
Bob /Nov. 1~2, |
|
|
|
Next Meeting |
|||
8:30pm EDT,
8:30am Taiwan, 10:30 Australia, 5:30pm Tucson/Thursday/Nov. 2. 2000 |
|||