AMiBA PROJECT WEEKLY MEETING
MINUTES
Date: 19,October 2000
Attendants: J.
Peterson, W. Wilson , M Kesteven, H. Wang , M.T. Chen, C.H. Lu, Y.J. Hwang,
C.W. Lu, P. Shaw,
J. Wang
Issues and Description |
Action by |
Output
|
|
MMIC- W- Band InP HEMT LNA |
|||
1. Regarding the
Sub Hamonic Mixer¡¦s chip test at ATNF, Mal says the target date to do that
test should be in the end of this month. 2. Huei says that
the first design for the InP HEMT MMIC is ready, and now is waiting for the
wafer test data from JPL. Todd told him that he needs two weeks more
to work out that test data. Fred says he will visit Pasadena in a week time. So Huei will inform Todd
about Fred visit and ask him to arrange an appointment with the person in NASA who is responsible for
the export license approval.
3. As for the
0.1um GaAs HEMT, Huei says they will finish the layout touch up and send the
chip out to TRW by Oct. 20. 4. As to the
export license application for the InP HEMT of TRW, Huei says Joyce told him
that the review process is still ongoing at the State Department He is
expecting to get a final decision on that issue by early November. 5. Wave-guide
filter ¡V Huei received some
experiment data from Mal by fax, Mal will provide some drawings to Huei as well, and Huei will forward those data
and drawings to Prof. Wu. This would be a good reference to Prof. Wu to develop his design in
parallel. (Mal is modifying the existing design of 80 GHz to 85 GHz as we need.) As for the prototype receivers,
Mal suggests Mingtang to investigate if he can find the required filters in the market. 6. As per NRAO¡¦s
request, we released a formal purchase order to NRAO for purchasing the 4
units of 82~106 GHz amplifiers. Mingtang will directly contact NRAO¡¦s
engineer in order to get some technical data, including the layouts of
amplifier. 7.Mal
says that he received a reminder the wafer is back this week, the plan is to
test more chips in the
next couple of weeks. All the hardware of the amplifiers blocks in
completed, so he expects to start to test that w-band InP LNA chips sometime
by end next week. So he hopes to work out some test results in three weeks. Huei says
Specek answered him by fax on 12 Oct., it is not possible to make the
conversion loss of the mixers lower above 100 GHz, and now the 2
mixer-doubler assemblies are ready to be shipped. Leo will talk to Prof. Chu
all about and ask him to make decision on relative contract issue. Huei says
that they have some back up plan, if ATNF could help us to package the mixers
we have, besides we have several design on going, including HBT, two HEMT
versions designed by Eugene. Warwick suggests we should keep the Specek one
for prototype using and design a better one by ourselves for production using.
Mingtang says
that considering the space restriction for receiver, we need to specify the
bias circuit as we purchase the relevant MMIC components. |
H. Wang M. Sinclair H.Wang K.Y. Lo H.Wang H.Wang M.Sinclair H. Wang M.T. Chen H.C. Lu MT. Chen H. Wang T.H. Chu H.C. Lu |
ongoing ongoing Oct. 20 ongoing ongoing ASAP ASAP ASAP ASAP |
|
Lag Correlator Hybrid |
|||
1. Jeff will
report by next. 2. Warwick says
that they have made some measurement on the HBT Gilbert Cell multiplier
wafer, the result is quite similar with the simulation, and he think there is
a possibility to use that multiplier up to 16 to 20GHz bandwidth. Warwick
will collect more measurement data, generate a report, and send over to Huei
and Jeff to take a look. 3. Paul, Eugene
and Leo met the ACX Company's people at the "Taitronic Exhibition"
on last Thursday¡¦s afternoon. They brought our inquiry back to the
headquarter for further study, and will give us an answer late this week.
Paul will keep on looking at it. 4. Warwick says he
got the low bandwidth prototype working now, got the first spectrum the other
day, and it is working quite nicely at the 3 GHz bandwidth, simulate the
result of Andy Harris shown. He is doing a test on it at this moment, trying
to figure out what the frequency response has on the performance. And he
thinks it looks quite promising to work with the 3 GHz bandwidth
correlator. 5.Huei says that they
finished the design work on the Gilbert Cells Multiplier, but there are some Problem unsolved. So he
will talk to Paul Robert to find out a solution. |
W.Warwick P. Shaw H. Wang |
ASAP ongoing ASAP |
|
Receiver |
|||
1.
Mingtang is working on the dewar layout; he is waiting for the mount
layout. He has not decided yet the overall size, because he is still waiting
for the data of some components in dewar, e.g. wave-guide. J.
Kingsley is working on the mount layout; Paul will contact Jeff to know the
status. Leo will speed up the components sourcing progress to collect
sufficient data in order to finalize the layout design ASAP. 2.
Mingtang received a mail from J. Payne about the collaboration on the
development of NRAO OMT. In this collaboration, U of Arizona machine shop
would make parts for 8 OMTs (3 for NRAO, 2 for Wollack and 3 for ASIAA); we
will pay three of the eight. NRAO provides drawings to the U. Arizona shop,
ASIAA assembly all of them and make the test. Wollack measures 2 units to
confirm the result. Mingtang and Yugene think we should be able to do the
testing. But for assembling, we should ask for a detail description. So,
Mingtang will ask John to provide a quotation and a detail assembly
description for OMT production. Jeff says that Wollack may be the only person
knows how to do it, and he also thinks this probably good for our people to
learn by doing it. 3.
Mingtang is also working on the feed horn design; he will work out
something and circulate to everyone to look at during this week. |
M.T.Chen P.Shaw H.C. Lu M.T. Chen M.T. Chen |
ongoing ASAP This week |
|
LO/IF |
|||
Eugene just
generates a NRAO visit report today; he will circulate it to everyone to look
at. We will put it on the ASIAA web site, and welcome
everyone to take a look and to comment. |
Y.J. Hwang |
ASAP |
|
Platform/Mount/Dishes |
|
|
|
1.Bob will send over a
draft layout for mount and dishes to everyone in a week or two after. 2.Jeff doesn¡¦t think the caesarian
could work with the 30cm antenna due to its high ground pick up. He will do some quantitative analysis to demonstrate this
case. 3.Regarding the height of
ground shield for our antenna, Bob requests Michael to ask their expert to
verify what size is good for us? 4.Mingtang says our new
engineer assistant C.W.Lu fould a local expert in the field of Hexapod. The expert, Prof. Perng, leading a lab in the Department of
Power mechanical Engineering of The Tsing-Hua University. Prof. Peng has more
than 10 years research experience on Hexapod, and he is very interest in the
AMiBA work. So Mingtang will invite him over to ASIAA to give a talk on what
he knows and what he think about our mount. |
B. Martin J. Peterson M.Kesteven M.T. Chen |
ASAP ASAP ongoing ongoing |
|
Site acquisition |
|||
Bob says that he plans to
visit Mauna Lao Observatory by the second week of November, to take a look on
site and see what the possibility is and how we proceed. |
B. Martine |
Ongoing |
|
Prototype
Specification and Project Book |
|||
1. He got some
contribution receiving drawings last day or two, we he will incorporate all
of these into a revised draft, he will send it to Fred and Paul by the end
of week. As a center source of all documentation there, and that is what has to be worked
with others for further contribution on all chapters. Fred will take over the question with. 2. Bob and Fred asks Michael,
Ravi and Bob to take a close look at some technical related science issues, e.g. UV coverage with current design on platform and drift
scanning techniques, observation strategy and photonic delay line. 3. Michael inputs some
comments on the antenna layouts; Philippe also feed something back to Michael
as well. As to the secondary mirror supporting structure, Jeff will collect
some material information and send it over to everyone to look at. |
B. Martin M.Kesteven J. Peterson |
Ongoing Ongoing ASAP |
|
Visitor |
|||
Darrel Emerson Oct. 9~11 / J. Payne Oct. 9~16 |
|||
Traveling |
|||
Bob / Oct.9 ~ Oct. 26,
Fred / Oct.14~Nov.1 |
|
|
|
Next Meeting |
|||
8:30pm EDT,
8:30am Taiwan, 10:30 Australia, 5:30pm Tucson/Thursday/ Oct. 26. 2000 |
|||