AMiBA PROJECT WEEKLY
MEETING MINUTES
Date: 5/Octomber/2000
Attendants: K.Y.
Lo, B. Martin, J. Peterson, W. Wilson , Bob Sault, M. Sinclair, M Kesteven, H.
Wang + 1 student, T.H. Chu, H.C. Lu, M.T. Chen, R. Wei, H.S.Li, C.H. Lu, P.
Shaw, J. Wang
Issues and Description |
Action by |
Output
|
MMIC- W- Band InP HEMT LNA |
||
1. Regarding the
Sub Hamonic Mixer¡¦s chip test at ATNF, Mal says that their lab is busy to
test the InP for HBT amplifiers at this moment, but he think that test will
be carried on before the end of this month. 2. Huei says that
the first design for the InP HEMT MMIC is ready, and now is waiting for the
wafer of JPL to see if they can do the second design. But definitely he will send
one of the design to JPL by early Nov. Huei will contact Todd, and Fred will
contact Charles Lawrence to find out the status about the NASA's
approval.
3. As for the
0.1um GaAs HEMT, Huei says they will finish the layout touch up and send it
to TRW by Oct. 20. 4. As to the export
license application for the InP HEMT of TRW, Huei says Joyce told him that
the review process is still ongoing at the State Department He is expecting
to get a final decision on that issue by early November. 5. Waveguide
filter ¡V Mal says he sent some experiment
data to Huei, Huei will check the fax machine after going back to school. 6. As for
purchasing the 4 units of 82~106 GHz amplifiers from NRAO, we sent a letter
to NRAO for export license application. Once the internal purchasing
procedure was completed we will release that order to NRAO. Paul says that
the internal purchasing process is still ongoing, and in the mean time we are
still waiting for NRAO¡¦s response about the export license approval. Fred
will ask NRAO to provide the dimension of amplifier, it is important for
Mingtang to design the receiver. 7. Mal says that
their lab is ready to test the rest of 6 units of w-band InP LNA, that test
result will be come out in two or three weeks. 8.Prof.
Chu says he didn't receive the Specek's amplifiers yet, but it should be
delivered by Oct. 20 according the notice of the local distributor. |
H. Wang M. Sinclair H.Wang K.Y. Lo H.Wang H.Wang M.Sinclair H. Wang P. Shaw K.Y. Lo M. Sinclair T.H.Chu |
ongoing ongoing ongoing ongoing ongoing ongoing ongoing ASAP ongoing ongoing |
Lag Correlator Hybrid |
||
1. Jeff says he
did some simulation on the wire attenuator and alumina, he sent over some
simulation data to Warwick by email a couple minutes ago. The next step is to
see the noise of mixers, he is ordering a couple of amplifiers to fit in the
two independent noise signals to mixers, and then to watch what the noise of
the output, and what is the offset. And mean while he is working on making
the 16 lag correlators. 2. Warwick says
that he is still waiting for the HBT Gilbert Cell multiplier wafers from TRW. 3. Warwick says
that he is thinking about how we might produce the lag correlators element,
he is recently looking at the low temperature cold pile ceramic technology
that is a possible way to do it. He found a company in Taiwan -¡§Advance
Ceramic X Corp.¡¨ manufacturing these things. So it¡¦s will be a good idea to
contact with them to see if they are possible to do it for us. Warwick will
send the company¡¦s web address to Paul, and Paul will take care of it to find
out the company, and contact with them. 4. As to the
design work for prototype, Warick says it¡¦s coming together, he got one
element going and the secondary one at this moment, he is calculating on
that, and putting on the other, signaling them and see how they are
going. 5. Ray Wei says he
has simplified the circuit and also completed the simulation for the IC
circuit. There are some problem about the frequency mismatch between master
PLL and slave VCO, so is trying to solve these problems. After that he will
start to design the digital part. 6.
Huei says that they just finish the design work on the Gilbert Cells
Multiplier, but it probably would not
meet with the design goal, and right now they are proceeding the touch
up stage, and it will be sent out in 2 or 3 weeks. In the mean time, he is
studying the HBT design, because they
have another run for the GaAs HEMT by late Dec. So he hopes to get some
experience on the HBT design
also. 7.Warwick
says he has been talking to Prof. Chiueh about the packing process for
prototype, he has a regular contact with Prof. Chiueh. He will forward the
communication he have Prof. Chiueh to Paul. So Paul can keep on tracking
these things. |
J. Peterson W.Warwick P. Shaw W. Wilson R. Wei H. Wang P. Shaw |
Ongoing ongoing next week ongoing ongoing ongoing ongoing |
Receiver |
||
1. Mingtang
inputs a draft receiver layout on his web page, the signal entrance and the
height of the main chamber is not decided yet. Leo is
working on the component arrangement with him. As to the interface between receiver and mount,
Bob will sent a platform layout drawing to Mingtang by next week. 2. Yugene says he only got a sheet of specs from
the Atlantic Microwave Company about the OMT, they only guarantee the band
width of 94~96 GHz. Bob suggests Yugene that he should talk to NRAO people
about the OMT while he visiting there. Bob will follow up that as well. |
M.T.Chen B. Martin Y.J. Hwang |
ongoing next week ongoing |
LO/IF |
||
1.Bob says that Eugene is on the air plan right
now, he is not here to report. Eugene got quite a lot of information of NRAO
in Tucson at his visit. He sketch up some new concept for photonic LO, he
will draw up and circulate around after he coming back. He also studies where
to locate the noise rejection to the calibration source. Mal says they have
the same problem there for w-band receiver, he had a little bit of look at
the possibility of coupler, and he will take care of that issue. 2.Eugene should make formal proposal on the
injection to the secondary, then we get together to discuss the present
concept. As to the phase switching issue, Eugene also discussed it with John
Payne in Tucson. It is a practical change to use a separate phase switch for
each antenna, but this approach will lost one of the advantage of the
photonic LO system. So we should discuss further with Eugene next week. |
Y.J. Hwang Y.J.Hwang |
ongoing next week |
Platform/mount/dishes |
|
|
1.Bob will send over a
draft layout for mount and dishes to everyone in a week or two after. 2.Jeff don't think the caesarian
could work with the 30cm antenna due to its high ground pick up. He will do some quantitative analysis to demonstrate this
case. 3.Regarding the height of
ground shield for our antenna, Bob requests Michael to ask their expert to
verify what size are good for us. |
B. Martin J. Peterson M.Kesteven |
ASAP ASAP ongoing |
Site acquisition |
||
Bob says that he plans to
visit Mauna Lao Observatory by the second week of November, to take a look on
site and see what the possibility is and how we proceed. |
B. Martine |
Ongoing |
Prototype
Specification and Project Book |
||
1. He got some
contribution receiving drawings last day or two, we he will incorporate all
of these into a revised draft, he will send it to Fred and Paul by the end
of week. As a center source of all documentation
there, and that is what has to be worked with others for further
contribution on all chapters. Fred will take over the question with. 2. Bob and Fred asks
Michael , Ravi and Bob to take a close look at some technical related science
issues, e.g. UV coverage with current design on platform, drift
scanning techniques, observation strategy and photonic delay line, etc. 3. Philippe's student generates
some of layout drawings for dish, Paul will put them on web site for everyone to look at. |
B. Martin M.Kesteven P. Shaw |
Ongoing Ongoing ASAP |
Travelling |
||
Bob / Oct.9 ~ Oct. 26 |
|
|
Next Meeting |
||
8:30pm EDT,
8:30am Taiwan, 10:30 Australia, 5:30pm Tucson/Thursday/ Oct. 12. 2000 |