AMiBA PROJECT WEEKLY
MEETING MINUTES
Date: 28/September/2000
Attendants: B.
Martin, J. Peterson, W. Warick, H. Wang + 1 student, T.H. Chu, M. Kesteven,
H.C. Lu, Eugene Hwang , H.S.Li, P. Shaw, J. Wang
Issues and Description |
Action by |
Output
|
MMIC- W- Band InP HEMT LNA |
||
1. Regarding the
Sub Hamonic Mixer¡¦s chip test at ATNF, Huei will contact Mal to check the
test result of the " isolation property" by early next week. 2. Huei says Todd
told him that their mask of InP HEMT MMIC might be delay to the early Dec, so
we might have time to work out another design, and he is willing to pay us as
well.
3. As for the
0.1um GaAs HEMT, Huei says they had a design review in last Saturday. In the
mean time, CIC/Taida keep on negotiating the contract with TRW. 4. As to the
export license application for the InP HEMT of TRW, Huei says Joyce told him
that the review process is still ongoing at the State Department He is
expecting to get a final decision on that issue by early November. 5. Waveguide
filter ¡V Mal says that they have
been doing some experiments with particular type of sorts there, due to the
cut off rate is not sufficient, they need to do some small work on that in a
couple of weeks more. He will send some of data to Huei to take a look. 6. As for
purchasing the 4 units of 82~106 GHz amplifiers from NRAO, we sent a letter
to NRAO for export license application. Once the internal purchasing
procedure was completed we will release that order to NRAO. Paul says that
the internal purchasing process is still ongoing. 7. Mal sys that
their lab will get ready to test the rest of 6 units of w-band InP LNA in a
week or two. 8. Prof. Chu says
he didn't receive the Specek's amplifiers yet, and the dead line is on this Friday, so he will check the status with
the local distributor. |
H. Wang H.Wang H.Wang H.Wang M. Sinclair P. Shaw M. Sinclair T.H. Chu |
ongoing ongoing ongoing ongoing ongoing ongoing ongoing ongoing |
Lag Correlator Hybrid |
||
1. For the 17 lag
correlator, Jeff starts the discussion with Gramic about making these tree
divider structure that they sent a email about, and we talked about two weeks
ago . They like the idea, but suggested that we should make the structure
with print resistors on synthetic substrate alumina, and that was discussing
on making the entire part on alumina mixer at all instead of using hybrid.
The alumina has an advantage of very good loss tangent. So they are
discussing it. If it works out the entire lag correlator would be shrink by 3
inches dimension, and that will be very nice if we could achieve that. So
that is the discussion they are having. Warwick says that the high dielectric
constant is an advantage making things smaller, but the problem is the
distortion with the wide bandwidth.
He agrees the use of print resistor will be the only way we are able
to do it for the 20GHz wide band correlator. And for the other substrates,
similar to alumina but having lower dielectric constant, may be not common
and a little bit expensive, but might be an option. 2. Warwick says
that he is still waiting for the HBT Gilbert Cell multiplier wafers from TRW. 3. Ray Wei says he
has simplified the circuit and also completed the simulation for the IC
circuit. There are some problem about the frequency mismatch between master
PLL and slave VCO, so is trying to solve these problems. After that he will
start to design the digital part. 4.
Huei says that they will finish the design work on the Gilbert Cells
Multiplier in two weeks, if this time that chip could not meet with the
design goal, they still have chance to make the second iteration, and to
solve the problems by next time. |
J. Peterson W. Wilson R. Wei H. Wang |
Ongoing ongoing ongoing ongoing |
Receiver |
||
1. Mingtang
says he is starting the purchasing process for the cold heads and some key components. 2. Yugene says he only got a sheet of specs from
the Atlantic Microwave Company about the OMT, they only guarantee the band
width of 94~96 GHz. Bob suggests Yugene that he should talk to NRAO people
about the OMT while he visiting there by next week, and Bob will follow up
that also. |
M.T.Chen Y.J. Hwang |
ongoing ongoing |
LO/IF |
||
1.Eugene says
that he prepared some draft block diagrams for photonic LO and photonic calibration source, and
he just sent them back to Taipei Jackie will distribute the copies to
everybody right after this meeting. 2.Eugene says
that as for the photonic LO system ,J. Payne and D¡¦Addario suggested to use the ¡§central unit
& distribution¡¨ instead of a conventional one, and this will reduce cost of the
whole system. There will be a further discussion with Bill Shallue about the
issue of ¡§antenna - side coupled configuration¡¨. |
Y.J. Hwang Y.J. Hwang |
ASAP ongoing |
30
cm antenna |
||
Michael says he
spoke to G. James, James is still working on the calculations for the small
antennas, and need a little while to work out the number we need, he thinks. |
M.Kesteven |
ongoing |
Platform/mount/dish |
||
Regarding the height of
ground shield for our antenna, Bob requests Micelle to ask their expert to
verify what size is good for us. |
M. Kesteven |
ASAP |
Site acquisition |
||
Bob says he
talked with John Barnes of the Mauna Lao Observatory last week. John is the
Station Chief of the MAO operation in Hilo. It sounds very promising that our
needs may mesh with what they look for in the use of the site. Bob says he is
planning to visit Hilo in November, to take a look at the application process
that we need to do. He hopes we could test the prototype over there by next
year. |
B. Martin |
ongoing |
Prototype
Specification and Project Book |
||
Bob distributed a draft
prototype plan to everyone by email on Sep. 27, discussion about this issue in the meeting is
summarized as below: l
System block diagrams ¡V Leo will update the diagrams in electronic
form. l
Delay line system ¡V for the prototype, we should leave it off later,
since we don¡¦t need it until the construction for all of the three platforms,
Bob says. l
System overview descriptions ¡V Michael will supply more details on
that area. l
Receiver ¡V Bob will ask Mingtang to add the layout drawings to the
receiver description in section 6. l
Photonic LO system & Calibration source¡V Yugene will input more
block diagrams after discussing with NRAO persons. l
IF system ¡V T.H. Chu says that he will provide the equalizer
information. l
Correlator ¡V Warwick says that he will write some information for the
prototype. Jeff suggests that we should not put our efforts on building the
prototype in module. Warwick agrees with Jeff¡¦s opinion, he says that we
should not go too far for the prototype. l
Computer control ¡V Michael says that he will provide some information
on the computer section.
|
B. Martin H.C. Lu M.Kesteven M.T. Chen Y.J. Hwang T.H. Chu W. Wilson M.Kesteven |
Ongoing ASAP ASAP ASAP Ongoing ASAP ASAP ASAP |
Travelling |
||
Yugene / Sep. 23 ~ Oct. 6;
Bob / Oct.9 ~ Oct. 26 |
||
Next Meeting |
||
8:30pm EDT,
8:30am Taiwan, 10:30 Australia, 5:30pm Tucson/Thursday/5. Oct. 2000 |
|
|