AMiBA PROJECT WEEKLY
MEETING MINUTES
Date: 21/September/2000
Attendants: B.
Martin, H. Wang + 3 students, T.H. Chu, M.T. Chen, M. Kesteven, M. Sinclair,
H.C. Lu, Eugene Hwang , Ray Wei, H.C.Li, P. Shaw, J. Wang
Issues and Description |
Action by |
Output
|
MMIC- W- Band InP HEMT LNA
|
||
1. Regarding the
Sub Hamonic Mixer’s chip test at ATNF, they got some results about
"conversion loss" and "return loss". Huei would like to
know is there any progress on the measuring of the "isolation
property". Mal says the test work is still ongoing, he hopes they could
work out something in the next week. 2. Regarding the
JPL's stuff, Todd Gaier sent a formal request to the JPL's headquarter to
request to loan us two modules of InP LNA MMIC. Huei says that s bad news
from Todd, the JPL’s head quarter rejected his request to loan the amplifiers
to us. However they told Todd that they will approve it if NASA approved it.
So Todd will send a request to NASA, but we don’t know the chance is. But
Todd told him that it is no change to put the InP HEMT MMIC on JPL's mask, so
Huei will finish the design by early November.
3. As for the
0.1um GaAs HEMT design work is still ongoing, all the chips will be sent to
CIC for reviewing by this coming Saturday, and CIC/Taida is still negotiating
the contract with TRW. 4. As to the
export license application for the InP HEMT of TRW, Huei says Joyce told him
that the review process is still ongoing at the State Department He is
expecting to get a final decision on that issue by early November. 5. Waveguide
filter – Mal says that they have
been doing some experiments with particular type of sorts there, due to the
cut off rate is not sufficient, they need to do some small work on that in a
couple of weeks more. He will send some of data to Huei to take a look. 6. As for
purchasing the 4 units of 82~106 GHz amplifiers from NRAO, we sent a letter
to NRAO for export license application. Once the internal purchasing
procedure was completed we will release that order to NRAO. Paul says that
the internal purchasing process is ongoing. 7. Mal sys that
their lab will get ready to test the rest of 6 units of w-band InP LNA in a
week or two. 8. Prof. Chu says
the local distributot of Specek told him the amplifiers as we ordered should
be delivered by the end of this month, he will keep on watching it. |
M. Sinclair H. Wang H. Wang H. Wang M. Sinclair P. Shaw M. Sinclair T.H. Chu |
ongoing ongoing ongoing ongoing ongoing ongoing ongoing ongoing |
Lag Correlator Hybrid |
||
1. For the 17 lag
correlator, Jeff starts the discussion with Gramic about making these tree
divider structure that they sent a email about, and we talked about two weeks
ago . They like the idea, but suggested that we should make the structure
with print resistors on synthetic substrate alumina, and that was discussing
on making the entire part on alumina mixer at all instead of using hybrid.
The alumina has a advantage of very good loss tangent. So they are discussing
it. If it works out the entire lag correlator would be shrink by 3 inches
dimention, and that will be very nice if we could achieve that. So that is
the discussion they are having. Warwick says that the high dielectric
constant is an advantage making things smaller, but the problem is the
distortion with the wide bandwidth.
He agrees the use of print resistor will be the only way we are able
to do it for the 20GHz wide band correlator. And for the other substrates,
similar to alumina but having lower dielectric constant, may be not common
and a little bit expensive, but might be an option. Warwick agrees to collect some information about the specs
of substrates, and send them to Jeff to look. 2. Warwick said he
is still waiting for the HBT Gilbert Cell multiplier wafers have been shipped
next week from TRW, so they he hope doing the wafer testing probably a couple
weeks of time. Then they will get some information on how well the HBT
Gilbert Cells would. 3. Ray Wei says he
has simplified the circuit and also completed the simulation for the IC circuit.
There are some problem about the frequency mismatch between master PLL and
slave VCO, so is trying to solve these problems. After that he will start to
design the degital part. 4. As to the simulation on
the Gilbert Cells Multiplier, Huei says that he got some comments by email on
that simulation result from Jeff and Warwick. He has more questions needed to discuss with Paul Roberts. |
J. Peterson W.Warwick R. Wei H. Wang |
Ongoing Ongoing ongoing ongoing |
Receiver
|
||
1. Mingtang
says he is starting the purchasing process for the cold heads and some key
components. 2.
Yugene says he only got a sheet of specs from the Atlantic Microwave Company
about the OMT, they only guarantee the band width of 94~96 GHz. Bob suggests
Yugene that he should talk to NRAO people about the OMT while he visiting
there by next week, and Bob will follow up that also. |
M.T.Cheng Y. Hwang |
ongoing ongoing |
LO/IF |
||
1. Eugene says due
to the optical delay line configuration is not clear to him, so he only
finish the diagram for LO noise source. He needs some inputs, e.g. the total
delays, tracking requirements. 2. Eugene says
that the purchasing process for the instruments and components are still
ongoing. 3.As to the IF,
Prof. Chu says he is making the equalizer for the cable which base on
George's design, he is also starting to design the layout fro the amplifier,
that amplifier is base on the HP 20GHz wide band. |
Y. Hwang Y.. Hwang T.H. Chu |
Ongoing Ongoing ongoing |
30 cm antenna |
||
Michael says he spoke to
G. James, James is still working on the calculations for the small antennas,
and need a little while to work out the number we need, he thinks. |
M.Kesteven |
ongoing |
Platform/mount
|
||
1. Base line - Bob
says that we should set up the limit for base line ASAP. Warwick says he did
few calculation based on the 20m value being around in the past week ; for
1.2m dishes, it seems to him is still within the range of setting the
correlator, so probably ok in this concern. Bob says he will propose this the
base line we move forward with 20m is the limit, and we start figure out the
delays and what is the application on the delay tracking on IF from there. 2. Bob proposes
another configuration for platform and mount, he suggests having 3 hexagonal
mounts with 2.5m wide platform.
There are some discussions about this issue as below: Warwick - we need to make the decision on how many
antennas we need to have 19 or 21 ? It does cause increase the size of
correlator by that a quarter, from 19 to 21, but it is not significant. He
think the major cost is coming from the modulate and de-modulate, and the
delay line itself is not such a large components cost. So initially, we will
build a compact antenna without any delay line on the platform, and then the
photonic IF system and delay line system can be sort out in the second
part. Michael - he like the
three platform suggestion, and he thinks we should concentrate on the CMB
platform as the first stage. This simplfies the development path- one
platrform, no delay lines and delay tracking machinery. During the first year
of CMB shakedown/observations we develop the SZ platform along with the delay
tracking machinery. And he also thinks that it could be save some cost if we
directly built a 2.5m platform for prototype. Jeff - he thinks
this idea is interesting, he also think 21 antennas doesn't change the
correlator significantly. |
B. Martin |
ongoing |
Site acquisition
|
||
Bob says he talked with
John Barnes of the Mauna Lao Observatory last week. John is the Station Chief
of the MAO opeation in Hilo. It sounds very promising that our needs may mesh
with what they look for in the use of the site. Bob says he is planning to
visit Hilo in November, to take a look at the application process that we
need to do. He hopes we could test the prototype over there by next
year. |
B. Martin |
ongoing |
Prototype Specification
and Project Book |
||
1. Ravi and
Michael will be join the today's science meeting to discuss some
observational technique relative issues with science team in order to get
some outstanding issues resolved more efficiently. 2. As to the
specification drafted by Michael, Bob hopes to put it out anybody else in the
court next week. |
B. Martin B. Martin |
ongoing Next week |
Travelling
|
||
Yugene / Sep. 23 ~ Oct. 6;
Bob / Oct.9 ~ Oct. 26 |
||
Next Meeting
|
||
8:30pm EDT,
8:30am Taiwan, 10:30 Australia, 5:30pm Tucson/Thursday/28 September 2000 |
|
|